Thursday, January 22, 2026

Capital budgeting. Investment Appraisal techniques

 very important, exam-oriented points for Investment Appraisal / Capital Budgeting from US CMA Part 2 (Strategic Financial Management). These are frequently tested concepts, MCQ traps, and numerical focus areas you should revise carefully.

 

1️⃣ Core Capital Budgeting Techniques (Must-Know)

🔹 Net Present Value (NPV) – MOST IMPORTANT

Accept project if NPV > 0

Uses time value of money

Assumes reinvestment at cost of capital

Preferred method by CMA exam

Mutually exclusive projects → choose highest NPV

📌 CMA trap: High IRR ≠ Best project (NPV wins)

 

🔹 Internal Rate of Return (IRR)

Discount rate where NPV = 0

Accept if IRR > Cost of Capital

Problematic when: 

o Non-conventional cash flows → Multiple IRRs

o Mutually exclusive projects

Assumes reinvestment at IRR (unrealistic)

 

🔹 Payback Period

Time required to recover initial investment

Ignores: 

o Time value of money

o Cash flows after payback

Discounted Payback considers time value

📌 Used mainly for liquidity & risk screening

 

🔹 Profitability Index (PI)

PI = PV of inflows / Initial investment

Accept if PI > 1

Useful under capital rationing

Conflicts with NPV in mutually exclusive projects

 

🔹 Accounting Rate of Return (ARR)

Based on accounting profit

Uses book value, not cash flows

Ignores time value

Least reliable method (theoretical weakness)

 

2️⃣ Cash Flow Estimation – High Exam Weight

🔹 Relevant Cash Flows

Include:

Incremental cash flows

Opportunity costs

Changes in working capital

Tax impacts

Terminal cash flows

Exclude:

Sunk costs

Allocated overheads

Financing costs (interest, dividends)

📌 Golden Rule: “Cash flows, not profits”

 

🔹 Initial Investment

Cost of asset

Installation & training

Increase in working capital

Less: sale of old asset (after-tax)

 

🔹 Operating Cash Flow

Two methods:

Net income + depreciation

EBIT × (1 − Tax rate) + Depreciation

 

🔹 Terminal Cash Flow

Includes:

Salvage value (after tax)

Recovery of working capital

After-tax salvage =

Salvage − Tax on gain (or + tax shield on loss)

 

3️⃣ Risk & Uncertainty (Frequently Tested)

🔹 Sensitivity Analysis

Changes one variable at a time

Identifies critical variables

Does NOT assign probabilities

 

🔹 Scenario Analysis

Best, worst & most likely scenarios

Considers multiple variable changes together

 

🔹 Probability-Based NPV

Expected NPV = Σ (Probability × NPV)

 

🔹 Decision Tree Analysis

Used for sequential decisions

Discount backward using expected values

 

🔹 Simulation (Monte Carlo)

Uses probability distributions

High computational but realistic

 

4️⃣ Cost of Capital – Direct Link with Capital Budgeting

🔹 Weighted Average Cost of Capital (WACC)

Used as discount rate

Reflects firm’s risk profile

Use project-specific cost of capital if risk differs

📌 CMA trap: Using company WACC for high-risk projects

 

5️⃣ Inflation & Capital Budgeting

Use consistency rule: 

o Nominal cash flows → Nominal discount rate

o Real cash flows → Real discount rate

Inflation increases future cash flows & discount rate

 

6️⃣ Capital Rationing

🔹 Hard Rationing

External constraints (loan limits, market)

🔹 Soft Rationing

Internal policy constraints

📌 Solution: Rank projects using Profitability Index

 

7️⃣ Replacement Decisions

Consider: 

o Opportunity cost of old asset

o Differential cash flows

o Ignore past costs

Evaluate incremental NPV

 

8️⃣ Mutually Exclusive Projects – Very Important

Conflicts between:

NPV vs IRR

PI vs NPV

Caused by:

Scale differences

Timing differences

📌 CMA Rule: NPV decision always prevails

 

9️⃣ Real Options in Capital Budgeting

Types tested:

Expansion option

Abandonment option

Timing option

Flexibility option

📌 Traditional NPV undervalues projects by ignoring options

 

🔟 Ethics & Strategic Considerations

Capital budgeting supports long-term strategy

Avoid earnings manipulation in project evaluation

Behavioral bias: Over-optimism in cash flows

 

📌 CMA Exam Focus Summary

Area Importance

NPV & Cash Flows ⭐⭐⭐⭐⭐

IRR & Conflicts ⭐⭐⭐⭐

Risk Analysis ⭐⭐⭐⭐

Replacement Decisions ⭐⭐⭐

Capital Rationing ⭐⭐⭐

Real Options ⭐⭐⭐⭐

 

www.gmsisuccess.in

US CMA Part 2 – Capital Budgeting / Investment Appraisal NUMERICAL MCQs with final answers (exam-oriented, calculation focused, CMA traps included).

 

📘 Numerical MCQs – Capital Budgeting (US CMA Part 2)

 

MCQ 1: NPV Decision

A project requires an initial investment of ₹5,00,000 and generates cash inflows of ₹1,50,000 per year for 5 years. Cost of capital is 10%. PV factor for annuity @10% for 5 years = 3.791.

What is the NPV?

A. ₹68,650

B. ₹(68,650)

C. ₹1,18,650

D. ₹(1,18,650)

Answer: ✅ A

Working:

PV of inflows = 1,50,000 × 3.791 = 5,68,650

NPV = 5,68,650 − 5,00,000 = ₹68,650

 

MCQ 2: Accept / Reject using IRR

A project has an IRR of 14%. The firm’s WACC is 12%.

Decision?

A. Reject

B. Accept

C. Indifferent

D. Need NPV to decide

Answer: ✅ B

📌 Rule: Accept if IRR > Cost of Capital

 

MCQ 3: Mutually Exclusive Projects

Project A: NPV = ₹2,00,000, IRR = 18%

Project B: NPV = ₹2,50,000, IRR = 16%

Which project should be selected?

A. Project A

B. Project B

C. Both

D. None

Answer: ✅ B

📌 CMA Rule: Higher NPV wins in mutually exclusive projects

 

MCQ 4: Payback Period

Initial investment = ₹4,00,000

Annual cash inflow = ₹1,00,000

Payback period?

A. 3 years

B. 4 years

C. 5 years

D. 6 years

Answer: ✅ B

Payback = 4,00,000 / 1,00,000 = 4 years

 

MCQ 5: Discounted Payback

Initial investment = ₹2,00,000

Cash inflow after 1 year = ₹1,10,000

PV factor @10% for year 1 = 0.909

Discounted payback after 1 year = ?

A. Fully recovered

B. ₹1,00,000 recovered

C. ₹99,990 recovered

D. ₹90,900 recovered

Answer: ✅ D

PV = 1,10,000 × 0.909 = ₹90,900

 

MCQ 6: Relevant Cost

A machine purchased 2 years ago for ₹3,00,000 has a current resale value of ₹80,000. It will be replaced.

What amount is relevant?

A. ₹3,00,000

B. ₹2,20,000

C. ₹80,000

D. Nil

Answer: ✅ C

📌 Opportunity cost = Current resale value

 

MCQ 7: Operating Cash Flow

EBIT = ₹2,00,000

Tax rate = 30%

Depreciation = ₹50,000

Operating cash flow?

A. ₹1,40,000

B. ₹1,90,000

C. ₹2,50,000

D. ₹1,75,000

Answer: ✅ B

OCF = EBIT(1 − T) + Depreciation

= 2,00,000 × 0.7 + 50,000

= 1,40,000 + 50,000 = ₹1,90,000

 

MCQ 8: After-Tax Salvage Value

Book value of asset = ₹1,00,000

Salvage value = ₹1,40,000

Tax rate = 30%

After-tax salvage value?

A. ₹1,40,000

B. ₹1,28,000

C. ₹1,12,000

D. ₹1,00,000

Answer: ✅ B

Gain = 40,000

Tax = 40,000 × 30% = 12,000

After-tax salvage = 1,40,000 − 12,000 = ₹1,28,000

 

MCQ 9: Profitability Index

Initial investment = ₹6,00,000

PV of inflows = ₹7,20,000

PI = ?

A. 0.83

B. 1.00

C. 1.20

D. 1.50

Answer: ✅ C

PI = 7,20,000 / 6,00,000 = 1.20

 

MCQ 10: Capital Rationing

Two projects require ₹5,00,000 each.

Project NPV

A ₹1,00,000

B ₹1,40,000

Only one project can be chosen.

Which project is preferred?

A. A

B. B

C. Both

D. None

Answer: ✅ B

📌 Higher NPV per rupee invested

 

MCQ 11: Expected NPV

Project NPVs:

Scenario Probability NPV

Best 0.3 ₹3,00,000

Normal 0.5 ₹1,50,000

Worst 0.2 ₹(1,00,000)

Expected NPV?

A. ₹1,50,000

B. ₹1,45,000

C. ₹1,60,000

D. ₹1,35,000

Answer: ✅ B

Expected NPV =

(0.3×3,00,000) + (0.5×1,50,000) − (0.2×1,00,000)

= 90,000 + 75,000 − 20,000 = ₹1,45,000

 

MCQ 12: Replacement Decision

Old machine resale value = ₹50,000

New machine cost = ₹4,50,000

Initial investment for replacement?

A. ₹4,50,000

B. ₹5,00,000

C. ₹4,00,000

D. ₹3,50,000

Answer: ✅ C

Net investment = 4,50,000 − 50,000 = ₹4,00,000

 

🔥 CMA Exam Tip

NPV + Cash Flow logic = Highest scoring area

Always ignore sunk costs

Use after-tax cash flows

Mutually exclusive → NPV rule only

 


www.gmsisuccess.in


ADVANCED & TRICKY US CMA Part 2 MCQs on Capital Budgeting / Investment Appraisal.

These are exam-level, focus on decision traps, mixed concepts, and numerical logic exactly as tested by IMA.

 

🔥 Advanced Tricky MCQs – Capital Budgeting (US CMA Part 2)

 

MCQ 1: IRR vs NPV Conflict (Scale Difference)

Project X requires an initial investment of ₹2,00,000 and generates ₹3,20,000 after 1 year.

Project Y requires an initial investment of ₹10,00,000 and generates ₹14,50,000 after 1 year.

Cost of capital = 12%.

Which project should be selected?

A. Project X (higher IRR)

B. Project Y (higher NPV)

C. Both projects

D. Neither project

Answer: ✅ B

Explanation:

NPV(X) = 3,20,000 / 1.12 − 2,00,000 = ₹85,714

NPV(Y) = 14,50,000 / 1.12 − 10,00,000 = ₹2,94,643

📌 CMA Rule: Mutually exclusive → Choose higher NPV

 

MCQ 2: Non-Conventional Cash Flows (Multiple IRR Trap)

A project has the following cash flows:

Year Cash Flow (₹)

0 (1,00,000)

1 2,30,000

2 (1,32,000)

Which method should be relied upon?

A. IRR

B. Payback

C. NPV

D. ARR

Answer: ✅ C

📌 Reason: Non-conventional cash flows → Multiple IRRs possible

NPV is always reliable

 

MCQ 3: Depreciation Tax Shield Impact

A machine costs ₹5,00,000, depreciated straight-line over 5 years with zero salvage.

Tax rate = 30%.

Annual depreciation tax shield equals:

A. ₹30,000

B. ₹50,000

C. ₹75,000

D. ₹1,50,000

Answer: ✅ C

Depreciation = 5,00,000 / 5 = 1,00,000

Tax shield = 1,00,000 × 30% = ₹30,000 ❌ (Trap)

Wait carefully 👇

Correct answer: A

📌 CMA Trap: Tax shield = Depreciation × Tax rate = ₹30,000

 

MCQ 4: Opportunity Cost Inclusion

A company owns land purchased years ago for ₹2,00,000.

The land can be sold today for ₹6,00,000.

The land will be used for a new project.

What amount should be considered in capital budgeting?

A. ₹2,00,000

B. ₹4,00,000

C. ₹6,00,000

D. Nil

Answer: ✅ C

📌 Opportunity cost = Current market value

 

MCQ 5: Working Capital Recovery Trap

A project requires an initial investment of ₹4,00,000 and working capital of ₹80,000.

Working capital will be fully recovered at the end of project life.

How is working capital treated?

A. Expense over project life

B. Ignored

C. Cash outflow at start & inflow at end

D. Depreciated

Answer: ✅ C

 

MCQ 6: Inflation Consistency Rule

A project’s cash flows are stated in real terms.

Which discount rate should be used?

A. Nominal WACC

B. Real WACC

C. Risk-free rate

D. IRR

Answer: ✅ B

📌 Consistency Rule:

Real CF → Real discount rate

 

MCQ 7: Replacement Decision – Sunk Cost Trap

An old machine was purchased for ₹4,00,000.

Its current book value is ₹1,00,000 and resale value is ₹70,000.

Which amount is relevant for replacement decision?

A. ₹4,00,000

B. ₹1,00,000

C. ₹70,000

D. ₹30,000

Answer: ✅ C

📌 Opportunity cost = resale value

 

MCQ 8: Capital Rationing Ranking

Projects under capital rationing:

Project Investment NPV

A ₹5,00,000 ₹90,000

B ₹3,00,000 ₹75,000

Which project should be selected first?

A. A

B. B

C. Both together

D. None

Answer: ✅ B

PI(A) = 0.18

PI(B) = 0.25

📌 Rank by Profitability Index

 

MCQ 9: Decision Tree Logic

Decision tree analysis is MOST useful when:

A. Projects have constant cash flows

B. Decisions are reversible

C. Sequential decisions depend on future outcomes

D. Capital rationing exists

Answer: ✅ C

 

MCQ 10: WACC Misuse Trap

A firm evaluates a high-risk project using company WACC.

This will most likely result in:

A. Correct NPV

B. Understated NPV

C. Overstated NPV

D. No impact

Answer: ✅ C

📌 High-risk project → Higher discount rate required

Using lower WACC → NPV overstated

 

MCQ 11: Abandonment Option

The ability to abandon a project early if it performs poorly is an example of:

A. Expansion option

B. Flexibility option

C. Timing option

D. Real option

Answer: ✅ D

📌 Specifically → Abandonment option

 

MCQ 12: Discounted Payback vs NPV

Which statement is TRUE?

A. Discounted payback is superior to NPV

B. NPV ignores time value

C. Discounted payback ignores cash flows after cutoff

D. Both are equally preferred by CMA

Answer: ✅ C

 

MCQ 13: Financing Cost Trap

Interest expense on project financing should be:

A. Included in cash flows

B. Ignored in capital budgeting

C. Deducted after tax

D. Treated as opportunity cost

Answer: ✅ B

📌 Financing costs are reflected in discount rate

 

MCQ 14: Mutually Exclusive – Timing Difference

Projects differ in timing of cash flows.

Which method correctly resolves the conflict?

A. IRR

B. Payback

C. NPV

D. ARR

Answer: ✅ C

 

MCQ 15: Terminal Year Tax Shield

A project ends with an asset having a salvage value below book value.

What occurs?

A. Tax liability

B. Tax neutrality

C. Tax saving

D. No cash flow

Answer: ✅ C

📌 Loss on sale → Tax shield

 

🎯 CMA Exam Strategy

If confused → choose NPV

Watch for sunk cost & opportunity cost traps

Capital rationing → PI

High risk ≠ Company WACC

Non-conventional CF → Ignore IRR

 


www.gmsisuccess.in


No comments:

Post a Comment